UPDATED TIMELINE AND CONTRACTS
Nativity Playground Renovation Committee Members:
As school ends and we move closer to activation of Phase II, here are some quick overall updates I wanted to share with you:
- The overall timeline has not changed since the last committee update:
- May 27 - Ordering of sport court tiling and materials/fitness stations
- June 10 - Final check on gas/power/cable lines for installation areas
- June 14-15 - Removal of basketball hoops/Installation of sport court cement base
- July 14-15 - Fitness station equipment installation and wood chip base
- July 18-19 - Installation of sport court tiles
- The above tentative timeline will be altered and fluctuate to address impending/potential inclement weather.
- A postcard promotion has been created to send out to Nativity families in the next week to encourage them to assist with the July 14-15 fitness station installation.
- The Karen and Chris Gehrig family has requested the basketball hoops that are being removed from the playground area on June 14-15. Northern Construction will remove them and set them off to the side for the Gehrig family to transport.
I am hoping that you will be available to help with the July 14-15 fitness station installation; at the very least, I hope that you will promote the July 14-15 installation to other Nativity families. There will be updates on the website as we get closer to installation and I will also send out an email that you can forward to others. We most likely will need 15-20 persons on these days of installation.
Is there anything I am missing at this point? Thanks again for all your help - we're almost there!
Peace, Lee
|